DMCI Works Double Time on Infra Projects

By D.M. Consunji, Inc. on September 3, 2019

Premier construction company, D.M. Consunji, Inc. (DMCI) is working double time to complete its big-ticket infrastructure projects to help boost the Build, Build, Build program of the Philippine government. 

 

As of June 30, DMCI has completed 61.93 percent of the entire LRT Line 2 East Extension project. The train viaduct was completed in 2017 while the two additional stations will be completed by next month. The last package which is funded by JICA is part of the government hybrid project.

 

This includes the electromechanical system (EMS) and trackworks needed to operate the four kilometer train line was awarded to the joint venture of Marubeni Corporation and DMCI last March.

 

“Marubeni has procured the EMS systems and we have started the installation works. Barring any unforeseen circumstances, we expect to finish the entire east extension project by the fourth quarter of 2020,” said DMCI President and CEO Jorge A. Consunji.  

 

The LRT Line 2 East Extension project was designed to accommodate an additional 80,000 passengers daily, one-third more than the current LRT 2 average daily ridership of 240,000.

 

Skyway Stage 3, another high-impact infrastructure project of DMCI, is 72.67 percent complete, as of June 30. Its Plaza Dilao off-ramp along Quirino Avenue in the City of Manila was opened to motorists last July 22.

 

DMCI expects to complete an additional 12.33 percent of the Skyway Stage 3 Section 1 and 2 by the end of the year, which will raise its year-end accomplishment to 85.00 percent.

More News

October 7, 2024

DMCI successfully completes IMS recertification

May 23, 2024

CIC inks P3.3-B deal with DMCI for C5 Link Segment 3B construction

October 15, 2023

DMCI supports Hooked on Book (HOB) Library

All News

DMCI is 13th GKK’s Regional Winner! October 16, 2024

DMCI successfully completes IMS recertification October 7, 2024

CIC inks P3.3-B deal with DMCI for C5 Link Segment 3B construction May 23, 2024

DMCI supports Hooked on Book (HOB) Library October 15, 2023

Continued Certification of DMCI’s Integrated Management System September 1, 2023

Continued Certification of DMCI’s Integrated Management System February 16, 2023

DMCI-Nishimatsu joint venture bags subway contract October 3, 2022

DMCI supports relief operations to typhoon-stricken areas January 9, 2022

DMCI on its way back to prepandemic profit level this year August 11, 2021

DMCI vaccinates over 4,000 employees July 9, 2021

From Ikea to Dagat-Dagatan: DMCI begins work on biggest wastewater facility March 19, 2021

Blessed Consunji Group pays it forward January 24, 2021

More than 5,000 youths to get skills training from USAID, PBEd; Aboitiz, DM Consunji to provide pre-employment support December 7, 2020

DMCI order book leaps 152% to P65.8 B in H1 August 14, 2020

Full blast construction of NLEX connector to start this year February 24, 2020

More firms eye bidding for Manila subway contracts February 24, 2020

MRP Foundation-funded PSG Station Hospital topped off February 24, 2020

First dedicated OFW hospital, diagnostic center begins construction in Pampanga February 20, 2020

DMCI Works Double Time on Infra Projects September 3, 2019

Ceremonial Track-laying for LRT Line 2- East Extension Project Package 3 April 16, 2019

Republic of the Philippines Award for Manila LRT Line 2- East Extension Project March 5, 2019